Residential

OverviewRooftop PV at volumeRoof & dronePlanes measured on the roofAttic & structureRafters recordedElectricalPanel and interconnectionDesign & engineeringModel to stamped setHomeowners: free monitoringAlready have solar? Free reviewUnderperformance checkFree tool for homeowners

Commercial & Industrial

OverviewBig roofs, real structureOn-site surveyRoof, structure, switchgearDesign & engineeringPE stampedVisual inspectionModule resolutionThermal inspectionFaults as heatElectroluminescenceCell-level cracks

Utility-Scale

OverviewThousands of acresLiDAR topographyTerrain before earthworkLand surveyingBoundary and topographicConstruction monitoringProgress, measuredThermal & ELEvery string

Across every scale

Site surveysRoof and electrical, one visitPermitting & engineeringStamped plan setsInspectionAerial thermal and ELShading analysisSA, TOF and TSRFSurvey locationsState and metro guides

The platform

Platform overviewPortal, 3D models, live dataFeature guidesWho it serves and how it worksShading analysisMove the sun yourselfCost calculatorWhat bad field data costs you

Sign in

Vanguard AccessInvite only · survey data portal

Solar reference

Solar questions answeredResidential, commercial and utility-scaleSurvey methodologySources, measurements and limitsCompany factsOfficial services and capabilities

Field Notes · build vs. buy

What a survey really costsPart 01 · the full modelUtilization is the whole gamePart 02 · a real TuesdayThe break-even headcountWhen hiring pays offTwo technicians, two roofsVariance, measuredThe hybrid crewIn-house plus outsourced

Field Notes · reference

Site survey checklistBuilt backwards from reworkHow long a survey takesHour by hourDo panels need a permit?What goes in the packageStorage site surveysThe capture listCompare survey vendorsQuestions to ask any vendor

Company

All servicesAll Field NotesAboutBook a 15-min call

Home  /  Field Notes  /  Electrical and interconnection survey

Field Notes · Commercial & Industrial

Electrical service and interconnection survey items for commercial PV

For commercial PV, the electrical service often decides system size before the roof does. The survey must capture the service voltage and configuration, switchgear and main ratings, bus rating, available fault current, transformer and meter details, usable space and clearances, and photographs of both a load-side and a supply-side interconnection option so the engineer can choose..

C&IElectrical8 min read

Short answer

For commercial PV, the electrical service often decides system size before the roof does. The survey must capture the service voltage and configuration, switchgear and main ratings, bus rating, available fault current, transformer and meter details, usable space and clearances, and photographs of both a load-side and a supply-side interconnection option so the engineer can choose.

Why the electrical room can cap the project

On a large commercial building the roof area is rarely the limiting factor. A distribution center may have more roof than any sensible array needs, while its main switchboard is full, its bus is rated tightly against its main breaker, and its transformer is owned and controlled by the utility. In that case the system is limited by the point of interconnection, not the number of modules that fit. A survey that records the roof carefully but treats the electrical room as a few photographs delivers half a record.

Start at the utility meter and work inward

The most reliable way to capture an electrical service is to follow the power. Begin at the utility transformer, then the service conductors, the meter and current transformer cabinet, the main service disconnect, the main switchboard or switchgear, and finally the distribution panels that the building actually uses. At each stop, record what it is, who owns it, and what it is rated for.

  • Transformer. Pad-mount, vault or pole-mounted, the nameplate kVA and impedance where visible, and the owner. A utility transformer is the utility's equipment and cannot be altered by the project.
  • Service voltage and configuration. Commonly 208Y/120 V or 480Y/277 V three-phase on commercial buildings. Record the actual configuration, including any high-leg delta service, which affects equipment choices.
  • Meter and CT cabinet. Meter location, meter number, and whether the utility seals the cabinet. Many utilities do not allow anyone but their own staff to open it.
  • Main service disconnect. Rating, manufacturer and model, plus the location relative to the meter.
  • Switchboard or switchgear. Manufacturer, model, bus rating, main device rating, short-circuit rating and the arrangement of the sections.
  • Available fault current. A label, an existing study or a utility letter. New equipment must have an adequate interrupting rating.

Load-side or supply-side: photograph both

A load-side connection lands the PV output on a breaker in the switchboard. It is limited by the busbar rules in NEC 705.12. A supply-side connection taps the service conductors between the meter and the main service disconnect under NEC 705.11 and is not subject to those busbar limits, but it needs physical room, a suitable tap method and utility acceptance. Which option works depends on details that only show up on site.

The survey should therefore capture the evidence for both. For a load-side option, photograph the bus labels, the available breaker spaces and the position of the main relative to any spare positions. For a supply-side option, photograph the service entrance area, the space around the meter and main, the conductor sizes visible, and any wall or ceiling that would constrain a tap. The engineer can then pick the best approach without sending the crew back.

Space, clearance and routing

Inverters, AC combiners, disconnects and sometimes a new transformer all need a home. The electrical code requires working clearances in front of equipment, so the available wall and floor space is smaller than it looks. Measure the proposed equipment location, the clear depth in front, headroom, and the path from the equipment to the point of interconnection.

Then record the conduit route from the array to the equipment. A commercial route may cross a roof edge, run down an exterior wall, pass through a mechanical room and cross a parking lot. Each leg needs a length, a penetration and an owner. Long runs change voltage drop and cost, so the engineer needs actual distances, not approximations from a satellite image.

Rapid shutdown and labeling constraints

Rapid shutdown under NEC 690.12 shapes the layout of conductors on and in buildings. Photograph where the array conductors would enter the building and where the rapid shutdown initiation device could sit. Also capture existing labels and any existing PV or generation equipment, because adding to an existing system brings additional rules.

What to ask the building owner

  • The electrical single-line diagram and any recent power studies.
  • Whether the service has been upgraded or expanded since the original drawings.
  • The utility account details and rate schedule, plus interval data if the utility provides it.
  • Planned loads such as EV charging, new equipment or an expansion, which change the right interconnection choice.
  • Shutdown windows, because a supply-side tap or switchgear change usually requires an outage.

Questions that change the interconnection plan

Several facts discovered during the electrical walk can change the whole plan, so it is worth asking about them deliberately. Is there an existing generator, battery or PV system on the service? Existing generation changes the busbar calculation and the labeling. Is the building served by more than one meter or service? A campus with several services may allow the system to be split. Is a service upgrade already planned? If so, the solar design may be able to piggyback on it instead of working around the old gear.

Also ask how the utility treats commercial interconnections in that territory. Application timelines, study requirements and technical standards differ between utilities, and the survey is a convenient moment to collect the interconnection contact and any published guidelines. The survey crew does not decide those questions, but a record that lists the utility, the account and the contact lets the engineer start the application promptly.

Finally, note the physical condition of the equipment. Corrosion, heat discoloration, loose or missing covers and outdated gear are worth flagging to the owner, because the engineer may recommend replacing equipment instead of connecting new generation to it.

Handing it to engineering

Electrical engineers read the record in a particular order: service and ratings first, then space, then routing. Organize the deliverable the same way, with legible nameplates, labeled photos and a short note calling out anything unusual. Our companion note on main switchgear photos and documentation goes into what a legible nameplate set looks like, and the survey-to-plan-set handoff note covers how the record becomes drawings.

Solar Survey AI captures the electrical room as part of a commercial on-site survey, alongside the roof and structure in one visit, with the deliverable 48 hours after the survey. C&I design and engineering then works from that record and is PE stamped. If you are scoping a project and are unsure whether the electrical service can support the system you have in mind, the electrical zone is the first place to look.

Questions we get about this

What electrical items does a commercial solar survey capture?

Service voltage and configuration, switchgear and main ratings, bus rating, available fault current, transformer and meter details, usable space and clearances, the conduit route, and photographs of both load-side and supply-side interconnection options.

What is the difference between load-side and supply-side interconnection?

A load-side connection lands on a breaker in the switchboard and is limited by the busbar rules in NEC 705.12. A supply-side connection taps between the meter and main disconnect under NEC 705.11 and avoids those limits, but needs space, a tap method and utility acceptance.

Why does available fault current matter?

New equipment must have an interrupting rating adequate for the fault current available at its location. The value usually comes from the utility, an existing study or an equipment label.

Can I open the utility meter cabinet during the survey?

Usually not. Many utilities seal the CT cabinet and only allow their own staff to open it. The survey photographs it from outside and records what can be seen legitimately.

Does a full electrical room mean no solar?

Not necessarily. A supply-side tap, a panel upgrade or a different point of interconnection may be possible, but the survey has to document the options so the engineer can evaluate them.

Related reading

More in Field Notes, or see every service.

Scoping a commercial roof?

Tell us the building, the roof area and the timeline. We will tell you straight what the survey needs to cover and whether we fit.

Book a 15-min call
Book a 15-min call